McCain/Westcoat Intersection Closure Starts Sept. 8

Post Date:09/03/2020 4:12 PM

Full Intersection Closure Anticipated - September 8, 2020 thru November 23, 2020

In an effort to minimize the construction impact on the residents in this area, the decision was reached on September 1 to convert the intersection from a partial to a full closure, thereby reducing the construction timeline. Council's decision to implement a full closure of the intersection has the potential to reduce the construction timeline by 28 weeks allowing the intersection to open before Thanksgiving, weather contingent. 

Full Closure: 11 weeks (75 calendar days)

Implement Full Closure of Intersection: Tuesday, September 8, 2020

Open Intersection to Traffic: Monday, November 23, 2020

Who do I contact if I have questions or concerns?

Construction Manager: Corey Lawson - 817.503.1093

Construction Inspector: Adilda Cazorla - 817.503.1102        

City Engineer: Larry Wright - 817.503.1095

Engineering Division: 817.503.1090 / engineers@colleyville.com