Full Intersection Closure Anticipated - September 8, 2020 thru November 23, 2020
In an effort to minimize the construction impact on the residents in this area, the decision was reached on September 1 to convert the intersection from a partial to a full closure, thereby reducing the construction timeline. Council's decision to implement a full closure of the intersection has the potential to reduce the construction timeline by 28 weeks allowing the intersection to open before Thanksgiving, weather contingent.
Full Closure: 11 weeks (75 calendar days)
Implement Full Closure of Intersection: Tuesday, September 8, 2020
Open Intersection to Traffic: Monday, November 23, 2020
Who do I contact if I have questions or concerns?
Construction Manager: Corey Lawson - 817.503.1093
Construction Inspector: Adilda Cazorla - 817.503.1102
City Engineer: Larry Wright - 817.503.1095
Engineering Division: 817.503.1090 / engineers@colleyville.com